· 3E051 Module 7 Study Guide
0 / 0 reviewed
// 3E051 · module 7 · contingency operations

Module 7
Study Guide

Comprehensive question bank built directly from the Module 7 transcript. Covers EALS, RADR, BEAR primary/secondary distribution, grounding, RALS, ROWPU, MAAS, and shelter systems.

200+
Questions
13
Topics
4
Lessons
Source: All questions are drawn directly from the 3E051 Module 7 Transcript (002) — Lessons 1 through 4. Click any question to reveal the answer and mark it reviewed. Color coding: cyan = EALS, red = RADR, amber = BEAR, green = RALS, purple = MAAS.
// lesson 1 · task 1 · 19.4.4
EALS Fundamentals
Reference: TO 35F5-3-17-1 / TO 35F5-3-17-2 / AFTTP 3-32.14
System Overview
E-01What is the EALS designed to do, and what are the maximum dimensions of a runway it can light?
The EALS (Emergency Airfield Lighting System) is designed to be a rapidly installed runway lighting system for contingency airfields and temporary locations that need temporary airfield lighting. It supports flying operations at night and during periods of reduced visibility. It can light a runway or Minimum Operating Strip (MOS) up to 150 feet wide by 10,000 feet long. Module 7, Lesson 1, Task 1
E-02What types of lighting does the EALS provide?
The EALS provides: runway edge lighting, approach lighting, threshold/end lighting, taxiway lighting, Precision Approach Path Indicator (PAPI) lights, Distance-To-Go (DTG) marker lights, and obstruction lighting. Module 7, Lesson 1, Task 1
E-03What power source provides power to the EALS, and what voltage does it supply to the constant current regulator?
The EALS receives power from two MEP 805A or B, 30 kilowatt, 50-60 Hertz tactical-quiet diesel driven generator sets. The generators supply 416 volts AC to the 20 kilowatt constant current regulator. Module 7, Lesson 1, Task 1
E-04What is the regulator rated at versus its factory-adjusted maximum output, and why is it limited?
While the regulator is rated at 20 kilowatts, it is factory adjusted for a maximum output of 13 kilowatts. This limits the output voltage and allows the use of smaller diameter cable. The reduced output does not support full or high intensity when all or most lights are in the complete 150 ft by 10,000 ft series circuit. Module 7, Lesson 1, Task 1
E-05How do the six EALS trailers fit on a C-130 aircraft?
The six air-transportable EALS trailers can fit within the space of three pallet positions on a single C-130 aircraft. The trailers can be safely towed at speeds under 25 mph on paved surfaces or 5 mph on unpaved surfaces, in a convoy of three or less. They are not designed for public roads (no taillights, brakes, or clearance lights). Module 7, Lesson 1, Task 1
E-06What components does EALS have a spare for?
Every component on the EALS has a spare component. This includes the generator, regulator, control panel, PAPI, strobe master/slave, and the Series Circuit Adapters (SCA). Module 7, Lesson 1, Task 1
Installation
E-07How many personnel are needed to set up EALS, and how are they organized?
Six people, 2 of which must be certified electricians, organized into four crews with two general-purpose vehicles, can set up the EALS. TEAM A and TEAM B each have one truck with three people (one is designated "TAG"). Two-person teams lay the series circuit cable and place equipment; TAGs follow on foot approximately 800 feet behind the trailer, connecting components. Module 7, Lesson 1, Task 1
E-08What does TEAM A install vs TEAM B in EALS setup?
TEAM A installs all PAPI lighting and approach lighting for a unidirectional runway/MOS. TEAM B sets up the regulator and generators. Both teams start at opposite ends and perform identical tasks except for these two differences. After runway installation, Team A's 4 people install taxiways while Team B's 2 install obstruction lights, then B returns to assist with taxiways. Module 7, Lesson 1, Task 1
E-09How are approach lights placed, and what equipment uses a 45W lamp and 45W isolation transformer?
Approach lights are placed every 200 feet beyond the threshold, in line with the centerline, for 800 feet. At the 1,000-foot bar location, the center light is placed 3 to 10 feet on the approach side of the nearest strobe slave. Approach lights use a clear lens, 45-watt lamp, and 45-watt isolation transformer (IL) — the same fixture as edge lights. Module 7, Lesson 1, Task 1
E-10Describe the approach strobe system configuration — master units, slave units, SCAs, and placement.
The approach strobe system contains 3 master strobe units (1 spare), 4 slave units, and 5 SCAs (1 spare). Place the master strobe unit and SCA at the 1,200-foot point beyond the threshold. Place slave units at the 1,000-foot and 1,400-foot points on the extended runway centerline. Point all strobes towards the approach. Module 7, Lesson 1, Task 1
E-11How do you determine the number of threshold/end light fixtures needed, and what are the threshold light specifications?
Divide the width of the runway or MOS by 10, then add one. The system contains 33 fixtures and 33 ILs (including one spare each) — enough for a 150-foot wide runway. Threshold lights use a split red and green glass lens, 120-watt lamp, and 100-watt IL. They are placed in two groups of five, symmetrically, within 10 feet of the usable surface end, spaced 10 to 15 feet apart. Lights are red toward the runway and green toward the approach. Module 7, Lesson 1, Task 1
E-12What are the edge light specifications, total quantity, and emergency spacing deviation?
Edge lights use a clear lens, 45-watt lamp, and 45-watt IL. The system contains 116 fixtures (4 spares) and 113 ILs (1 spare) — enough for a 10,000-foot runway plus seven approach lights each end. Position ILs outboard of fixtures; place fixtures inside edge markers, up to 10 feet from edge. In emergency conditions, spacing up to 300 feet apart is an allowable deviation (standard is 200 feet; greater than 200 feet requires two cable segments). Module 7, Lesson 1, Task 1
E-13Describe PAPI approach angle standards and placement requirements.
The standard PAPI approach angle is 3.0°, with the normal range between 2.5° and 4.0° (may exceed 4.0° for local conditions). PAPI units are placed on the left side of the runway as viewed from the approach end, no closer than 50 feet to a runway, taxiway, or apron. The inboard unit centerline is 50 to 60 feet from the runway edge; the outboard unit is 20 to 30 feet from the inboard unit. Beam centers must be within 1 inch of a horizontal plane. Module 7, Lesson 1, Task 1
E-14What are the DTG marker light placement rules?
The DTG system has 10 45-watt ILs and unidirectional fixtures accepting 45-watt PAR lamps. Place lights every 1,000 feet, starting 1,000 feet from the runway end, up to the 5,000-foot marker. Signs are located on the right side of the runway as viewed from the approach end, 25 to 50 feet from the edge (or no more than half the runway width, whichever is less). Keep DTG markers away from PAPI units to reduce pilot confusion. Module 7, Lesson 1, Task 1
E-15What are the taxiway light specifications and normal vs. emergency spacing?
Taxiway lights use a blue lens, 30-watt lamps, and 45-watt ILs. The system includes 40 light fixtures, 40 ILs, and 250 reflectors. Position fixtures no more than 10 feet from the taxiway edge, spaced 50 feet apart in straight sections and 25 feet apart in curves. Emergency deviation allows spacing up to 220 feet in straight sections or 100 feet in curved sections. A critical WARNING: ensure the runway circuit is de-energized and disconnected from the regulator before installing taxiway lights. Module 7, Lesson 1, Task 1
E-16What are the grounding requirements for EALS generators and regulators?
Ground the generators, regulators, and control panel. If a ground is not present, install three 3-foot ground rods supplied with the system. Connect a separate ground cable from the ground rod to each generator and regulator. Power and control connections must be per T.O. 35F5-3-17-1. Module 7, Lesson 1, Task 1
E-17Where should the regulator be placed relative to the runway, and what limits cable length to generators?
The regulator should be placed preferably 200 to 600 feet from the runway, with a minimum distance of 60 feet. The total length of the power cable plus control cable connecting generators to the regulator cannot exceed 1,000 feet. The auxiliary fuel supply is placed within 25 feet of the generators. Module 7, Lesson 1, Task 1
E-18What alternate power source can the EALS regulator use besides MEP 805 generators?
The regulator can be powered from any other source capable of providing a minimum of 15 kVA, 240/416 VAC. The series circuit powers all EALS lighting equipment except obstruction lights. The series circuit uses a #10 AWG conductor. Module 7, Lesson 1, Task 1
E-19Describe the obstruction light system — how many lights, what type, and how are they deployed?
The obstruction light system has 10 battery-powered blinking red lights. If there are more than 10 obstructions, place them at the 10 most significant. Airfield operations must be informed of all obstructions. Installation: install batteries, survey for 10 most prominent obstructions, turn each unit's switch to ON, and place at obstructions. Module 7, Lesson 1, Task 1
Operation & Intensity Settings
E-20What are the initial switch positions before starting the EALS?
On the regulator panel: Intensity selector switch (S1) to REMOTE; Master circuit breaker (CB1) to OFF (down). On the control panel: GENERATOR CONTROL — OFF; GEN1/GEN2 REMOTE START — OFF; GENERATOR SELECTION — AUTO; LIGHTING CONTROL — OFF; STROBE CONTROL — OFF. Module 7, Lesson 1, Task 1
E-21What is the EALS intensity setting guidance based on visibility conditions?
Visibility intensity settings: Night over 4 miles → LOW; Night 3 to 4 miles → MEDIUM; Night under 3 miles → HIGH. Adjust as necessary based on pilot request. Module 7, Lesson 1, Task 1
E-22What is the generator startup sequence, and how long do you wait before starting the backup?
Turn GENERATOR CONTROL to ON. Turn REMOTE START of primary unit to AUTO — the RUN and ONLINE indicators should light. Wait 5 seconds, then turn the REMOTE START of the backup generator to AUTO. Then turn CB1 on the regulator panel to ON, set LIGHTING CONTROL to desired intensity, then set STROBE CONTROL to 1-18 or 19-36 depending on which strobe set is needed. Module 7, Lesson 1, Task 1
E-23What are the three EALS shutdown methods and when is each used?
System Blackout: Used when airfield is under attack — press SYSTEM BLACKOUT switch; lights go out immediately but generator keeps running. Reset with BLACKOUT RESET. Normal Shutdown: LIGHTING CONTROL OFF → regulator CB and intensity switch OFF → let generator run 3 minutes no-load → REMOTE START OFF → GENERATOR CONTROL OFF. Emergency Shutdown: At control panel (GENERATOR CONTROL OFF or BLACKOUT button), at regulator (CB OFF or intensity to OFF), or at generator (EMERGENCY STOP button). Module 7, Lesson 1, Task 1
Maintenance & Troubleshooting
E-24What are the regulator short circuit test current value limits at each intensity step?
Using the male-to-male adapter to short output plugs and an ammeter, output current should be within: LOW: 4.66 to 4.94A; MEDIUM: 5.33 to 5.67A; HIGH: 6.40 to 6.70A. If values are outside these limits, the regulator needs service. Module 7, Lesson 1, Task 1
E-25What does the open circuit test verify, and how quickly must the protective device respond?
The open circuit test verifies the open-circuit protective device works. With the lighting circuit disconnected from output plugs, turn CB ON, set intensity to LOW — the open-circuit protective device should automatically de-energize the regulator in less than 2 seconds. After de-energizing, turn intensity to OFF — the protective device should reset. Repeat to confirm, then reconnect the lighting circuit. Module 7, Lesson 1, Task 1
E-26Why must strobe capacitors be discharged before servicing, and what is the flash tube replacement procedure?
Capacitors installed in strobe systems carry an electrical charge and must be discharged prior to servicing to prevent injury or death. Procedure: de-energize system, open door and turn on/off switch to OFF, short the capacitors, grasp flash tube by base and pull straight out, install new tube (do not touch glass with hands), close and latch door. Also check for internal/external damage, corrosion, and interlock switch/door latch operation. Module 7, Lesson 1, Task 1
E-27What is the troubleshooting process for a complete loss of a strobe segment?
Possible causes: (1) Strobe control transmitter/receiver failure — check strobe selector; if both segments fail repeatedly, replace control panel; if one fails, check timing for failed segment. (2) Improper generator frequency — check frequency at panel; if not 60 Hz, adjust with manual speed control. (3) SCA failure — check SCA output voltage with true-RMS voltmeter; if not between 228–264 VAC and runway circuit works, change SCA. (4) Strobe master unit failure — replace master. Module 7, Lesson 1, Task 1
E-28What is the process for troubleshooting an open circuit in the EALS series circuit?
Turn power OFF. Visually check for open conditions — reconnect or replace. If open not visible, sectionalize the circuit: disconnect home run cables from regulator. Disconnect series cable at fixtures on opposite sides of runway; pull ends to the "middle" and reconnect to form a smaller circuit. Re-energize — if that segment lights, the open is in the omitted portion. If it doesn't light, the open is in the tested segment. Continue segmenting and testing until the open is found; replace faulty components. Module 7, Lesson 1, Task 1
E-29What are generator cold weather operations requirements below 0°F?
Generators start/operate from 0°F down to -25°F without a winterization kit. Below -25°F, operate the winterization kit (heater) before startup. Never add water to a battery unless you immediately operate the engine for at least 1 hour (water may freeze). Insulation becomes brittle in extreme cold — disturb wiring as little as possible. Allow generator to warm up to operating temperature before applying load. Lubricate per cold weather guidelines. Module 7, Lesson 1, Task 1
E-30What is the PAPI lamp replacement procedure?
Ensure the lighting circuit is de-energized first. Disconnect all cables; remove front securing knobs. Loosen the four wing nuts on hood clamps and slide clamps free. Remove 9 screws from hood; lift hood straight up. Remove electrical connections by pushing in connector and turning counter-clockwise. Remove lamp by compressing retaining springs while turning lamp counter-clockwise; withdraw from rear of reflector. Install new lamp in reverse. Module 7, Lesson 1, Task 1
// lesson 1 · task 2 · 19.6.1
Rapid Airfield Damage Recovery
Reference: AFPAM 10-219v4 / AFTTP 3-32.12 / AFTTP 3-32.17
R-01What is the purpose of RADR and what is it a subset of?
The purpose of RADR (Rapid Airfield Damage Repair) is to rapidly repair aircraft operating surfaces and localized infrastructure to recover operations at an airfield after an attack. It is the essential element enabling air base resiliency and continuation of airfield operations. RADR is a subset of Airfield Damage Repair (ADR). Reference: AFPAM 10-219v4. Module 7, Lesson 1, Task 2
R-02What are the three interrelated sub-processes (phases) of RADR?
RADR consists of: (1) Rapid Damage Assessment (RDA) — identify and characterize damage and hazards; (2) Rapid Explosive Hazard Mitigation (REHM) — neutralize UXO within and near repair zones; (3) Rapid Damage Repair (RDR) — repair selected pavement damage and establish the MAOS. The REHM and RDR phases are conducted concurrently to maximize time compression. Module 7, Lesson 1, Task 2
R-03What is the maximum MAOS dimensions RADR can establish?
RADR can establish a Minimum Airfield Operating Surface (MAOS) up to 150 feet by 10,000 feet, associated taxiways, ramps, access routes, and critical infrastructure. The scope of rapid crater repair varies proportionally to the intensity of the attack. Module 7, Lesson 1, Task 2
R-04What is the difference between a spall and a camouflet?
A spall is surface damage which does not penetrate the pavement base course. A camouflet is a cavity formed from a deep underground burst with minimal surface rupture. Camouflets are detected during the RDA assessment phase as they may not be visible on the surface. Module 7, Lesson 1, Task 2
R-05What are the six steps of crater repair in sequence?
The six crater repair steps are: (1) Debris removal; (2) Upheaval marking; (3) Pavement cutting; (4) Pavement breaking and excavation; (5) Backfilling; (6) Capping. Each step has a dedicated crew that performs the same repair step on all craters in the repair zone before the next crew moves in — an assembly line concept. Module 7, Lesson 1, Task 2
R-06When does debris removal begin, and how far must debris be cleared around and from the MAOS?
Debris removal begins immediately after the PAR sweep has proceeded at least 250 feet beyond the first crater. Clear debris at least 15 feet from around each crater. After debris is removed from around each crater, push it at least 30 feet from the edge of the MAOS. The debris removal team must stay ahead of the upheaval marking crew. Electricians may be used to operate a loader. Module 7, Lesson 1, Task 2
R-07What is upheaval marking and why is it critical?
Upheaval marking identifies upheaved pavement around craters — which is not always visible to the eye. Upheaval determination is accomplished through crater profile measurements (CPM). Unremoved upheaval will most likely fail under traffic and create FOD hazards. Reference AFTTP 3-32.17 for craters under 20 feet diameter; T.O. 35E2-5-1 for craters 20 feet or larger. Module 7, Lesson 1, Task 2
R-08What is pavement cutting and why is it the most critical step?
Pavement cutting is performed by two compact track loaders with wheel saw attachments following upheaval marks. It is the most critical step regarding meeting timelines because it directly impacts excavation and capping efficiency. Removing more pavement than necessary increases repair time and exhausts materials. A conventional walk-behind concrete saw may be required when dowels or rebar are in the saw path. Electricians may be used as spotters. Module 7, Lesson 1, Task 2
R-09What is the "slash and splash" backfilling technique?
Backfilling uses flowable-fill (a medium strength, high viscosity, excavatable, rapid-setting cementitious material). The "slash and splash" technique: suspend a 3,000-pound super sack of flowable fill over the excavated area, slash the bottom to release material into the repair, then splash with 50 gallons of water until reaching the prescribed depth. Crushed stone may be used as an alternative but requires more time, equipment, and personnel. Module 7, Lesson 1, Task 2
R-10What capping materials are used and what alternative caps are allowed on aprons/taxiways?
Standard caps: concrete cap (using volumetric mixer with rapid-setting concrete) or asphalt cap (produced by asphalt recyclers, compacted with rollers). Alternative caps: AM-2 matting may be used on aprons and taxiways (not high-speed taxiways or intersections); Fiber-reinforced Polymer (FRP) mat panels may be used depending on aircraft type, operations, and location. Neither alternative is as durable as asphalt or concrete. Module 7, Lesson 1, Task 2
R-11What are the spall repair criteria and procedures?
A spall qualifies for expedient repair if it: does not penetrate the full pavement thickness to the underlying base course, is not larger than 5 feet in diameter, and does not cause upheaval in surrounding pavements. Spalls are repaired by removing debris and loose material from in and around them, then placing rapid-setting repair material ensuring the final repair is level with the surrounding pavement. Thousands of spalls are expected after an attack. Module 7, Lesson 1, Task 2
R-12What is the electrician's specific role during each RADR step?
Electricians may be used: Debris removal — operating a loader with multi-purpose bucket; Pavement cutting — as a spotter (using shovel, cutting alignment aid, dust mask; ground target stands, remove debris from shroud/track path, inspect saw bits); Pavement breaking — as spotter (clean corners, level excavation bottom, measure/mark backfill depth); Backfilling — as helper (utility knife, rake, shovel); Capping — as helper/vehicle operator for front-end loader, CTL, steel roller, pneumatic roller. Module 7, Lesson 1, Task 2
R-13What is REHM and what capabilities do EOD teams use?
REHM (Rapid Explosive Hazard Mitigation) neutralizes UXO within and near repair zones. EOD personnel operate platforms and systems that allow surface and subsurface UXO positive identification, neutralization, collection, removal, and disposal. Automated systems reduce the UXO threat to Airmen and assessment timeline. Reference: AFTTP 3-32.5v6 for EOD UXO Operations guidance. Module 7, Lesson 1, Task 2
R-14What happens after all RADR processes are complete regarding the EALS and AAS?
FOD removal teams follow behind RDR teams. After FOD is cleared, marking and stripping crews identify and mark installation locations for the Aircraft Arresting System (AAS) and Emergency Airfield Lighting System (EALS). These teams work simultaneously to restore required capability. FOD is removed from the MAOS by scraping, sweeping, and vacuuming all surfaces until accepted by Airfield Operations. Module 7, Lesson 1, Task 2
R-15What is the RADR assembly line concept?
The RDR process is based on an assembly line concept where the assembly line (repair crews) moves from crater to crater. Each step has a dedicated crew performing that same repair step across all craters in the repair zone before moving. This uses optimized techniques and rapid-setting materials to minimize Mean Time to Repair (MTR) for both asphalt-concrete (AC) and Portland Cement Concrete (PCC) surfaces. Module 7, Lesson 1, Task 2
R-16What is an RDA, and what automated systems support it?
RDA (Rapid Damage Assessment) identifies and characterizes damage and hazards by collecting and analyzing data — number, location, and types of craters; UXO; and other damage. Assessments use both manual and automated data collection systems. Automated systems reduce the UXO threat to Airmen and reduce assessment timeline. Data collected selects the most appropriate MAOS to repair. Reference AFTTP 3-32.12 for MAOS selection and AFTTP 3-32.11 for airfield damage assessment. Module 7, Lesson 1, Task 2
R-17What is the MAAS installation sequence relative to RADR operations?
After RADR processes are complete, marking and stripping crews simultaneously mark locations for both the AAS (MAAS) and EALS installation. The grader makes a single coverage sweep about 15 feet wide, 1,400 feet down the centerline overruns for approach lighting placement access. A path is cleared 15 feet wide to the PAPI location and 25 feet wide to AAS installation locations. Module 7, Lesson 1, Task 2
R-18What pavement cutting reference is used for craters of different sizes?
For craters with apparent size less than 20 feet in diameter: reference AFTTP 3-32.17. For craters with apparent size of 20 feet in diameter or larger: reference T.O. 35E2-5-1. The measurement of full excavation depth must be reported and marked on walls using spray paint before backfilling begins. Module 7, Lesson 1, Task 2
R-19When is RADR considered modular and scalable?
RADR is a modular and scalable team-based process that can: support thousands of combat sorties for all airframes, provide temporary to semi-permanent repair options in all pavement conditions, and support employ-in-place and expeditionary capabilities. The scope varies proportionally to the intensity of the attack. Module 7, Lesson 1, Task 2
R-20What is the FOD removal process for the first 300 feet of the MOS vs. the remainder?
The first 300 feet (most critical area) of the MOS is cleared with a vacuum sweeper. The next 800 feet may also be cleared with a vacuum sweeper if possible. The remainder of the MOS is cleared with kick broom sweepers or two grader passes. A better standard is required on parking aprons and uphill taxiway sections because aircraft use more power there and are more likely to suck up debris. Module 7, Lesson 1, Task 4
// lesson 1 · task 3 · 19.6.2
Roller Procedures
Reference: RADR Rolling Sequence / Asphalt Capping
RP-01What is a "pass" in roller operations, and what is the overlap requirement?
A pass is equal to traveling across the repair and then returning to the original starting position. Perform each pass across the entire width of the repair. Overlap the previous pass by approximately 12 inches until the entire repair cap has received the pass — similar to making half-lapped layers when making tape splices. Maximum rolling speed: 3 mph. Avoid sharp turns, quick starts, and stops. Module 7, Lesson 1, Task 3
RP-02What is the correct rolling sequence for asphalt capping?
The rolling sequence: (1) ½ pass with steel-wheel roller (no vibration); (2) Two ½ passes with steel-wheel roller, vibration ON (asphalt must be ≥150°F); (3) 2 passes with pneumatic roller; (4) 3 passes with steel-wheel roller, no vibration. The helper trims excess asphalt with a square-head shovel between passes. Module 7, Lesson 1, Task 3
RP-03When should vibration be turned off during rolling, and what adjustments are made?
Turn off vibration, add an additional ½ pass, and decrease 2½ passes to 2 passes if: cracking is noted in the mat OR there is evidence of chipping on concrete edges, grooves, or joints. Never vibrate while the roller is stationary or on hard pavement. Module 7, Lesson 1, Task 3
RP-04What is the purpose of the pneumatic roller in RADR?
The pneumatic roller is used on step 3 of the RADR rolling process on asphalt, comprising 2 passes over the crater. It simulates heavy traffic flow and squeezes any remaining air pockets out of the repair. It is only used during asphalt capping. Pneumatic roller passes may be skipped if time is an issue or for smaller repairs (8½ to 12 square feet). Module 7, Lesson 1, Task 3
RP-05What are the key steel wheel roller safety rules?
Key safety rules: Only climb onto/leave the machine when stationary; operate engine at low idle for 5 minutes before shutdown (lets hot areas cool); braking is accomplished using forward/reverse lever; never vibrate while stationary or on hard pavement; never allow passengers; keep out of the zero-clearance area (right and left steer pivot area) — presence there when turning causes injury or death; wear hard hat and protective glasses; stop engine when refueling. Module 7, Lesson 1, Task 3
RP-06What are the runway cleanliness standards from "dirtiest/fastest" to "cleanest"?
From dirtiest/fastest to cleanest: (1) One fast grader coverage only — dirtiest but fastest; (2) Slow (2-3 mph) grader then faster (3-5 mph) grader — dirty, more large stones left; (3) One fast grader then tractor with front-mounted broom at ~5.5 mph — clean (ineffective if debris is wet); (4) One fast (4-5 mph) grader, then two vacuum sweeper passes at 3.5-4 mph — cleanest. Module 7, Lesson 1, Task 4
RP-07What is the required asphalt temperature for vibration-on roller passes?
For the vibration-ON steel wheel roller passes (two ½ passes), the asphalt temperature should be 150 degrees Fahrenheit or greater. Rolling below this temperature with vibration can damage the mat. Module 7, Lesson 1, Task 3
RP-08What FOD removal vehicles and equipment are normally used?
FOD removal equipment includes: Grader, Tractor Trailer, Dozer, Front End Loader, Industrial Tractor with Kick Broom, CTL with Kick Broom, and Vacuum Sweeper. Any piece of equipment with a bucket or blade can also be used to clear debris. Always perform vehicle operational inspections before use, refuel after use, and return to duty locations when tasks are complete. Module 7, Lesson 1, Task 4
RP-09How wide is the haul lane cleared by FOD teams and where is all debris moved?
FOD teams split into 2 crews (augmented by one loader from each crater repair team). Each crew clears a 25-foot wide convoy and material haul lane down the entire MOS. The RADR OIC and Crater Chief direct which side of the MOS the haul lane will be cleared. All debris is moved to the opposite side. After clearing the haul lane, teams clear the threshold and departure ends. Module 7, Lesson 1, Task 4
RP-10What is the purpose of the one FOD team rule?
One FOD removal team supports all RADR capabilities. For example, a medium RADR capability has only one FOD removal team to support all repair teams. They may be augmented with debris removal equipment. Sweepers run continuously during RADR and sweeping ceases only after the entire RADR process is complete — aircraft activity and winds continually blow additional debris onto the strip. Module 7, Lesson 1, Task 4
// lesson 1 · task 4 · 19.6.3 (cont.)
FOD Removal
Reference: Module 7 Transcript, Lesson 1, Task 4
F-01What is the purpose of the FOD removal process in the RADR context?
The FOD removal process removes large and small debris from convoy routes, crater repair areas; performs initial and simultaneous sweeping on the airfield and around crater repair areas; and performs final sweeping before aircraft trafficking can begin. It is essential because even small pieces of sharp metal can damage aircraft tires. Module 7, Lesson 1, Task 4
F-02What is the grader coverage path toward PAPI and AAS locations after haul lane clearing?
The grader makes a single coverage sweep about 15 feet wide, 1,400 feet down the MOS overrun centerline for approach lighting access. Additionally: a path 15 feet wide is cleared from the MOS to the PAPI installation location; a path 25 feet wide is cleared from the MOS to the AAS installation locations. Module 7, Lesson 1, Task 4
F-03Where is a higher standard of sweeping required and why?
A higher standard is required on parking aprons and uphill sections of taxiways because aircraft use more power at these locations and are more likely to suck up debris through jet blast/engine ingestion. A kick broom sweeper or second grader will be used for coverage at these locations. Module 7, Lesson 1, Task 4
F-04Why must shrapnel be removed even if debris appears minimal?
It is essential to sweep all areas to be trafficked by aircraft — even if debris appears minimal — because even small pieces of sharp metal can damage aircraft tires. FOD can catastrophically fail tires during takeoff and landing, potentially causing aircraft loss. Module 7, Lesson 1, Task 4
F-05What are the five key vehicle procedures to follow during FOD operations?
(1) Perform vehicle operational inspections and take action for discrepancies; (2) Always refuel vehicles after use; (3) Return vehicles to duty locations or staging areas when tasks are complete; (4) Sweep all areas to be trafficked by aircraft even if debris appears minimal; (5) Continuously run sweepers until the entire RADR process is complete. Module 7, Lesson 1, Task 4
F-06Describe the relationship between FOD teams and crater repair teams' loaders.
FOD teams are augmented by one loader from each crater repair team during the haul lane clearing phase. After the threshold and departure ends are cleared, crater repair team loaders return to their respective teams. This temporary augmentation allows faster initial clearance while not permanently removing equipment from repair operations. Module 7, Lesson 1, Task 4
F-07What is the minimum broom speed for an effective clean surface pass?
For a clean surface, the tractor with front-mounted broom should travel at approximately 5.5 mph. Speed is effective only if debris is mostly dry — a broom cannot produce a good clean surface if debris is wet and sticky. This pass follows a fast grader coverage to achieve a clean (not just "dirty") runway surface. Module 7, Lesson 1, Task 4
F-08What are the vacuum sweeper speeds for the cleanest surface standard?
The cleanest surface standard is achieved with: one fast grader pass at 4-5 mph, followed by two vacuum sweeper passes at 3.5-4 mph. This is the most time-intensive but produces the highest-quality clean surface. The first 300 feet of the MOS always gets the vacuum sweeper regardless of overall standard used. Module 7, Lesson 1, Task 4
F-09When does the FOD removal process begin relative to PAR sweep?
Debris removal begins immediately after the PAR sweep has proceeded at least 250 feet beyond the first crater to be repaired. This removes as much FOD as possible from all airfield pavements to be used for launch and recovery purposes. Sweepers run continuously from this point until the entire RADR process is complete. Module 7, Lesson 1, Task 4
F-10When is the FOD removal process accepted as complete?
FOD removal is accepted as complete when the MAOS surfaces are cleared of FOD and accepted by Airfield Operations. Sweeping does not cease until the entire RADR process is complete — aircraft activity and winds continually blow additional debris across the airstrip, so active sweeping must continue throughout operations. Module 7, Lesson 1, Task 4
// lesson 2 · task 1 · 19.2.6.1.1
BEAR Primary Distribution System
Reference: TO 35F14-1-1 / TO 35CA2-2-10-1
BP-01What voltage is the BEAR primary distribution system, and what is the two-phase installation approach?
The BEAR primary distribution system operates at 4,160 VAC. The two-phase approach: Phase 1 — provides power to critical facilities (airfield, command post, kitchen, water plant, fire department) using low-voltage MEP generators. Phase 2 — establishes the high-voltage distribution system; the power plant and associated equipment are installed. Module 7, Lesson 2, Task 1
BP-02What are the two methods of arranging a BEAR distribution system, and what are the advantages of each?
Radial layout: individual branch lines run from the PSC to each SDC. Advantages: requires less material, manpower, and time. Disadvantage: susceptible to attack — one shell can disrupt large areas. Used for small contingencies and initial deployment. Loop layout: two or more PSC feeder circuits supply power to the customer; SDCs physically connected. Advantages: two or more paths for current flow — inherent resistance to complete power outages. Disadvantage: more material and time to construct. Module 7, Lesson 2, Task 1
BP-03What is the BPU and what does it replace? What are its key specifications?
The BPU replaces the MEP-12 Generator. It is a fully enclosed, trailer-mounted, mobile, diesel-driven generator capable of 4,160/2,400 VAC using a three-phase four-wire system. Rated at 800 kW at 4,160/2,400 VAC at 60 Hz; 435 kW at 3,800/2,200 VAC at 50 Hz. Maintains rating at altitudes up to 4,000 feet and temperatures from -25 to 122°F. Up to 12 BPUs may be paralleled (9,600 kW at 60 Hz). Module 7, Lesson 2, Task 1
BP-04What are the three BPU operating modes?
Isochronous: Provides constant voltage and frequency; used when paralleling with other BPUs. Droop: Allows variable voltage and frequency; allows BPU to sync with other generators such as a MEP-12. Utility: Allows parallel operation with a utility power grid (commercial power grid). Module 7, Lesson 2, Task 1
BP-05What are the BPU grounding requirements and ground grid specifications?
Each BPU contains three 3-foot ground rod sections. Drive the ground rod 8 feet or more into earth, within 6 feet of the BPU, leaving a minimum of 6 inches above ground. When using more than one BPU, create a central ground grid by connecting all BPUs' ground rods together with #2 AWG copper conductor ground grid cable. Connect ground cable from the slotted chassis ground stud on the rear of the BPU to the ground rod. Module 7, Lesson 2, Task 1
BP-06What is the PSC, and how many ways does it have?
The PSC (Primary Switching Center) is a high-voltage switching station serving as a connection point between power plant generators and primary distribution circuits. It has six connections called "ways." Each way may be either a switch or a combination of switch and circuit breaker. Ways 1 and 2 are load interrupter switches only (used as generator inputs); Ways 3-6 have fault interrupter capabilities. The PSC uses SF6 gas insulation. Module 7, Lesson 2, Task 1
BP-07What are the factory fault interrupter current settings for PSC Ways 3-6?
Factory settings: Ways 3, 4, and 5: 200 amps (based on 1/0 AWG cable current limitations). Way 6: 340 amps (for paralleling 2 PSCs to support 4 BPUs or MEP-12s). If using 500 MCM copper tie cable, settings are increased to 590 amps, and 600-amp deadbreak cable terminations are required. Ways 3 and 4 share one overcurrent control unit; Ways 5 and 6 share the other. Module 7, Lesson 2, Task 1
BP-08What are the three switch positions on a PSC way, and why is the viewing window important?
The three positions are: Grounded, Open, and Closed. The viewing window allows you to visually verify the connection of the way. Look for the orange colored metal that is part of the movable switch blade. The grounded position is towards the operation side; the closed position blades are on the connection side. The voltage indicator at the top is charged by sunlight or a bright flashlight. Module 7, Lesson 2, Task 1
BP-09What is SF6 gas in the PSC and what happens if it leaks?
SF6 (sulfur hexafluoride) provides the electrical insulation within the PSC switch tank. If the tank is punctured or leaks, the SF6 escapes, losing the insulation. If a way is operated without SF6, internal switch contacts will pull an arc and flash over, causing damage to the operator and bystanders. Check the SF6 level by opening the viewing window of Way 1 — ensure the gas gauge is in the green zone. Module 7, Lesson 2, Task 1
BP-10What is the SDC-HV and what voltage transformation does it perform?
The SDC (Secondary Distribution Center) is the main point for distribution of secondary voltage. It contains a dry-type transformer that steps down 4,160 VAC primary to 120/208 VAC, three-phase, low-voltage power. Maximum SDCs per circuit: 5 SDCs when fed directly from a high-voltage generator; 6-10 SDCs per feeder when using standard PSC distribution. Module 7, Lesson 2, Task 1
BP-11What is the high-voltage cable used in BEAR primary distribution and how is it packaged?
The cable is #1/0 AWG, 5-kV, aluminum, cross-linked polyethylene (XLP) high-voltage cable with a single conductor and concentric ground. Each cable pallet contains three reels with 3,000 feet of cable per reel. Cable jacket is labeled for a specific phase (A, B, or C) to maintain proper phase relationships. Bury cables at least 18 inches deep when possible; at least 3 feet deep under roadways. Module 7, Lesson 2, Task 1
BP-12What are the SDC tap connections and what voltage loss can they compensate for?
The SDC primary windings have seven tap connections: two steps above and four steps below 4,160V. The tap changes can compensate for up to a 629-volt loss and still provide proper voltage on the secondary side. This is important when SDCs are placed at ½-mile intervals or more, requiring voltage drop compensation. Module 7, Lesson 2, Task 1
BP-13What are the LOTO-equivalent steps (Isolate-Block-Tag) for BEAR primary distribution?
ISOLATE: Analyze and find solutions; open and de-energize circuit to isolate the section to be worked. BLOCK: Physically prevent switches from operating: remove feed-through EFDs, remove fused EFDs, apply locks to PSC 3-way switches, park elbows on stands, install terminal bushing covers on unused bushings. TAG: Place AF Form 979 (Danger Tag — protects against accidental energizing) or AF Form 980 (Caution Tag — identifies abnormal configurations). Module 7, Lesson 2, Task 1
BP-14What does inspection of energized PSC/SDC equipment allow, and what is strictly prohibited?
Inspection of energized equipment is limited to looking, listening, and smelling. Look for: blue or purple corona halos (in darkness). Listen for: popping, crackling (electrical discharge), humming (resonance). Smell for: ozone (corona) or overheating organics. Strictly prohibited: removing any panel, barrier, or partition — removing bolted panels while energized could result in serious injury or death. Module 7, Lesson 2, Task 1
BP-15What PPE is required during all PSC operation phases?
Always wear at least Class 2 rubber gloves and appropriate arc-flash PPE (normally 40 cal) during all PSC operation phases. If sizzling or crackling sounds come from the PSC during load application or under full load, remove loads and de-energize the unit immediately. Module 7, Lesson 2, Task 1
BP-16What is "tracking" in a PSC, and what happens when it occurs in epoxy insulators?
Tracking is an electrical discharge caused by bridging insulators phase-to-phase or to ground — usually a surface phenomenon. In PSC epoxy cast insulators, tracking causes the epoxy to melt to a non-conducting surface, extinguishing the arc. However, the insulator should be replaced as soon as possible. When carbon lines or erosion craters become visible in epoxy insulators, the insulator has been damaged beyond repair by extensive electrical discharge bombardment. Module 7, Lesson 2, Task 1
BP-17What are the SDC maintenance frequencies for structures, access doors, panels, HV section, and transformers?
SDC maintenance schedule: Structures — semiannually (free of structural damage, corrosion, paint good, storage clean); Access Doors — quarterly (free of damage, corrosion, hinge lubricated, latch/friction good, door seal attached); Access Panels — quarterly (free of damage, corrosion, all fastening hardware in place); HV Section — quarterly (loadbreak connectors, bushing wells, EFD switches/fuses, ground connections); Transformers — semiannually (compartment clean, tap connections secure). Module 7, Lesson 2, Task 1
BP-18What is the L0 bushing on the BPU and why is it not used in BEAR?
The L0 bushing is the neutral connection in the BPU's wye (Y) configuration. It is not used in the BEAR primary distribution system because the BEAR primary distribution does not utilize the neutral even though it is a wye configuration. Only L1, L2, and L3 connections are made for the three-phase connections. Module 7, Lesson 2, Task 1
BP-19What is the DCS on the BPU and what functions does it provide?
The DCS (Digital Control System) is the brain of the BPU. It consists of five multifunction soft keys, alarm silence toggle, panel lights, AC circuit interrupt, unit or parallel, and fault reset. The multifunction switch has OFF, remote, local, and start positions plus an emergency stop button. The DCS provides: configuration and operation, annunciation, fault and warning reporting, and emergency stop control. In remote mode, up to 12 BPUs can be operated with the ROP software. Module 7, Lesson 2, Task 1
BP-20What is "tracking" and what type of distribution is preferred for BEAR after initial establishment?
Good practice is to quickly establish the base in a radial pattern, then come back and install loop conductors once the installation is operational. The loop cables are normally left in the open, de-energized position and are only used when needed. Like home station switching operations, ensure all electric shop personnel are accounted for and aware of abnormal conditions before switching. The PSC is not repairable in the field — only at depot level. Module 7, Lesson 2, Task 1
BP-21What are the BPU site placement requirements?
BPU placement requirements: select a smooth, level surface capable of supporting the BPU's weight; minimum 15 feet of clearance all around for maintenance; no overhead obstructions; close enough for paralleling cables to connect between all BPUs (standard cable is ~80 feet). Locate generator sets as far apart as feasible. Decompression doors at bottom must be closed; engage parking brakes, chock wheels. Module 7, Lesson 2, Task 1
BP-22What is the EFD in the SDC and how does removing the center EFD isolate the transformer?
EFD = Electric Fusible Disconnect. There are three sets of EFDs per phase (A, B, C), each group of three controlling: Output 1, the transformer primary (center, fused at 30A), and Output 2. The center EFD controls the transformer primary winding and includes a fuse. By removing only the center EFD of each set, you isolate the transformer while maintaining service to remaining SDCs in the circuit through the feed-through bushings. Module 7, Lesson 2, Task 1
BP-23What is the MEP 805A/B and what systems does it typically power?
The MEP 805 is a 24/30-kilowatt generator capable of providing 120/208V, three-phase power. It typically supplies power to the kitchen set and the Emergency Airfield Lighting System (EALS). The "A" suffix indicates analog components; the "B" suffix indicates digital controls. The MEP 800 series generators are also known as Tactical Quiet Generators (TQG) due to their noise reduction design. Module 7, Lesson 2, Task 2
BP-24What is the ground rod specification for MEP generators, and what are the two other acceptable grounding methods?
Solid ground rod: minimum diameter 5/8 inch, driven to minimum depth of 8 feet. Buried metal plate: ¼-inch thick, minimum area of 9 square feet, buried at minimum depth of 4 feet; ground lead at least #6 AWG copper. Metal water pipe: At least 10 feet in contact with earth, minimum ¾-inch diameter; supplement with a metal rod or buried plate. Module 7, Lesson 2, Task 2
BP-25How do you change generator phase rotation if it's incorrect?
To change phase rotation: (1) Turn off power; (2) Disconnect any two generator leads; (3) Switch their positions (if disconnecting A and C, connect C to A's position and A to C's position). After interchanging leads, retest with the phase rotation meter to confirm correction. For MEP-807A and MEP-809A, you must also program the auto voltage regulator (AVR) for the applicable voltage when reconfiguring. Module 7, Lesson 2, Task 2
BP-26What voltage drop percentage does the NEC recommend limiting for branch circuits, and how is it calculated?
The NEC recommends limiting voltage drop for branch circuits to 3 percent. Calculation: (Voltage difference) ÷ (Power supply voltage) = Voltage drop percent. Example: 120V supply, 108V at motor = 12V difference. 12 ÷ 120 = 0.10 or 10% — unacceptable. The BEAR system limits individual branch circuits to a maximum length of 800 feet to limit voltage drop to no more than 3%. Module 7, Lesson 2, Task 2
BP-27What are the MEP 806A, 807A, and 809A generators used for?
MEP 806A: 50/60 kW — mission essential power for small cantonment operations (up to 750 personnel, usually up to 3 months). Powers ROWPU, communications centers, command post, aircraft support, computers. MEP 807A: 100/83 kW — same missions as 806A but greater load; used when more than 750 personnel or load requires mobile prime power. MEP 809A: 200/166 kW — same mission requirements as 806A but provides greatest load capabilities. All can produce 120/208 or 240/416 VAC at 50 or 60 Hz. Module 7, Lesson 2, Task 2
BP-28What is the SDC high-temperature override switch and when is it used?
The SDC has a high-temperature override circuit: if transformer primary windings overheat, the shunt-trip main circuit breaker trips to prevent damage. The override switch allows the technician to bypass the shunt trip mechanism to apply power to the secondary bus during maintenance and troubleshooting. This switch is used ONLY during maintenance and troubleshooting — NEVER during normal operations. Module 7, Lesson 2, Task 2
BP-29What is the AMMPS and what generators make up this series?
The AMMPS (Advanced Mobile Medium Power System) is being fielded to add to and replace the 800 series MEP generators. Key units: MEP-1060 — diesel/JP-8 powered, 30 kW at 60 Hz (25 kW at 50 Hz), skid-mounted, EPA compliant. MEP-1070 — diesel/JP-8 powered, 60 kW at 60 Hz (50 kW at 50 Hz). Both are lightweight, electronically controlled. Mission critical loads are supported with 30 kW and 60 kW AMMPS generators. Module 7, Lesson 2, Task 2
BP-30What is the voltage reconnection panel and how does it work for 30-200 kW MEP generators?
The voltage reconnection panel allows the alternator windings to be connected in series or parallel to obtain two different voltage values from a single generator. Series: voltage increases, current stays constant (240/416V). Parallel: voltage stays constant, current increases (120/208V). Before startup, ensure the reconnection board arrow matches the customer's voltage arrow. Ensure ALL nuts are tightly screwed down before operation. On 3-15 kW generators, voltage adjustment is via a selector switch instead. Module 7, Lesson 2, Task 2
// lesson 2 · task 2 · 19.2.6.2.1
BEAR Secondary Distribution System
Reference: TO 35CA2-2-10-1 / TO 35F14-1-1
BS-01What are the secondary output specifications of the SDC, and how many output circuits does it have?
The SDC secondary has 16 120/208-volt output circuits, each capable of supplying 60 amps per phase. Secondary feeder cables are five-wire, #6 AWG copper with 600-volt THW insulation rated at 60 amps. The 200-amp MEP input connects to the SDC from a MEP generator. The mechanical safety interlock prevents both breakers (main and mission essential) from being ON at the same time. Module 7, Lesson 2, Task 2
BS-02What is the caution regarding transferring from MAIN to MISSION ESSENTIAL power?
CAUTION: Never transfer from MAIN to MISSION ESSENTIAL power under load. The MEP generator may remain connected during normal operations when the SDC receives 4,160-volt primary power. However, the transfer must be performed with no load applied. Lethal voltages are present at the load connection board during operation — never connect or disconnect load leads while the generator is operating. Module 7, Lesson 2, Task 2
BS-03What are the PDP sizes available and what are the connection types for smaller vs. larger PDPs?
PDPs are available in: 15 kW, 25 kW, 30 kW, 60 kW, 100 kW, and 200 kW. The 15, 25, and 30 kW PDPs use smaller 60-amp cannon plug connections. The 60, 100, and 200 kW PDPs may need to be hard-wired through the bottom or use the larger 200-amp cannon plug connections. Larger PDPs can serve as sub-distribution centers to other PDPs and major loads. Module 7, Lesson 2, Task 2
BS-04What are the secondary cable sizes, lengths available, and maximum recommended run length?
Secondary cables come in 200-amp and 60-amp sizes. The 200-amp cable is 25 feet long and connects the low-voltage MEP generator to the SDC. The 60-amp cables come in lengths of 25, 50, and 100 feet. When installing, limit secondary runs to 150 feet when possible to reduce voltage drop. General practice limits any branch circuit to maximum 800 feet. Total cable distance from generator to point of use should not exceed 800 feet. Module 7, Lesson 2, Task 2
BS-05What does each tent in the BEAR base receive for lighting and outlets?
Each tent receives a lightweight distribution box fed from a PDP by a 50-foot, 20-amp cable with twist-lock connection. Each tent gets: one light streamer (six lights spaced along the streamer) and two convenience outlet assemblies (one per side of tent). The distribution panel has a single-pole toggle switch protected by a 20-amp circuit breaker. Two GFCI 20-amp circuit breakers protect the outlet streamers. Module 7, Lesson 4, Task 1
BS-06What is the 25 kW PDP associated with, and what are its connections?
The 25 kW PDP is associated with the small shelter system. It has: one 120/208-volt cannon plug input, one 120/208-volt cannon plug output (usually for an ECU), four 20-amp 120-volt outputs for lighting, and one 25-amp 120-volt convenience outlet. The 15 kW PDP has: one 120/208-volt input, one 120/208-volt output for ECU, and twelve 20-amp 120-volt outputs for lighting/outlets. Module 7, Lesson 2, Task 2
BS-07What is the SDC MEP power connection and how long can a low-voltage MEP power the SDC before the HV grid must be installed?
The SDC can accept power from a low-voltage MEP generator through the 200-amp MEP input connection (mission essential circuit breaker) for up to 15 days or longer before the high-voltage grid is installed. Apply load gradually by closing circuit breakers one at a time. A phase indicator light failing to come on means return the MAIN breaker to OFF and check fuses and lamps for the affected phase. Module 7, Lesson 2, Task 2
BS-08What troubleshooting step applies when transformer high temp light is illuminated with no secondary power?
If no 208 VAC secondary power and transformer high temp light is illuminated: transformer may have overheated and tripped the main breaker. Action: allow transformer to cool, check and remove overload, then reset the main breaker. If A, B, C bus energized indicators are not lit: possible blown fuse or broken/burned lamps — check and replace blown fuses; if lamps still don't light, check and replace bulbs; if still not lit, check transformer output. Module 7, Lesson 2, Task 2
BS-09Where is the distribution box mounted in a BEAR SSS tent, and why?
The distribution box is mounted approximately 4 feet high, next to the personnel door, adjacent to the ECU return inlet. This location allows easy access to the switch controlling the lighting streamers. The box may be bolted to or through the tent frame. Velcro straps attach streamer cables to the tent frame, normally at each arch. The 3 cables (female connectors) connect string lights and receptacles; they should be approximately 2 feet high along the arch frame. Module 7, Lesson 4, Task 1
BS-10What generator starting procedures apply to the MEP 806A/B CIM display screen?
Hold ENGINE CONTROL switch in START (2 seconds). Observe CIM display until oil pressure reaches at least 25 psi, voltage has increased to approximate rated value, and engine has reached stable speed. Release to PRIME & RUN. Check WATER TEMP (170–200°F) and OIL PRESSURE (25–60 psi). Warm up without load for 5 minutes if possible. Adjust voltage and frequency to required values. Press GFCI TEST button — ensure RESET is in the IN position. Module 7, Lesson 2, Task 2
BS-11What is the indicator lights significance on PDPs and what cannot be relied on solely?
PDPs have voltage indicator lights to identify if a particular phase is energized. These indicator lights are NOT to be the sole identifier for determining if a circuit is energized. Always verify with an appropriate meter. Basic PDP operation consists of switching circuit breakers ON or OFF as needed; the panel board is powered by the PDP's main breaker. Module 7, Lesson 2, Task 2
BS-12What are the cable safety installation rules for BEAR base secondary cables?
Key cable safety rules: bury cables or place them to prevent tripping hazards; install inside tents/expedient structures to prevent electrical hazard; place lights and cables low enough for occupants to reach but high enough so no one walks into them; cables must be in place and securely connected at each end before being energized; when connecting to SDC, start at the bottom and work up; ensure enough cable to reach any output cannon plug if needed. Module 7, Lesson 2, Task 2
BS-13What generator shutdown steps must be followed before turning off the DC disconnect?
Shutdown sequence: Turn off supplied load → push AC Circuit Interrupt to OPEN (confirm CONTACTOR POSITION reads OPEN) → turn local master control to OFF → operate engine without load until cool-down mode ends (unit shuts down by itself) → push emergency stop in → turn OFF DC electrical disconnect AFTER power-down sequence is complete. Failure to wait may result in damage to equipment. Then inspect coolant/oil, check for leaks, perform maintenance. Module 7, Lesson 2, Task 1
BS-14What SSS shelter dimensions and wind load ratings apply?
The Small Shelter System (SSS) measures 32 feet 6 inches long × 20 feet wide × 10 feet high when fully erected. It can withstand steady wind loads of 50 knots and gusts up to 60 knots. Its lifespan is 10 years when erected long-term and has a 20-year shelf life. If used in areas with winds over 40 mph, guy ropes are required — drive 18-inch anchors approximately 36 inches from the side, angled with top away from the shelter. Module 7, Lesson 4, Task 3
BS-15What is the procedure for removing BEAR tent electrical systems?
First, de-energize by disconnecting the power source (PDP or SDC) before starting any component removal. Disassembly is performed in reverse order of installation. Clean items as thoroughly as possible during teardown; allow wet components to dry before packing (prevent mold). All cords and components must be put back into proper storage containers so all parts are accounted for next deployment. Replace frayed cables — frayed conductors can cause electric shock or fire. Module 7, Lesson 4, Task 1
BS-16What is the base squaring measurement for the SSS base assembly?
To square the SSS base, measure 38 feet 3 inches from outside corner to outside corner using the diagonal method with a rope or tape measure. Drive 18-inch double-headed spikes through spike holes in the base frame to secure the assembly. Do NOT drive a spike through the center end base pieces — that hole is used for the end panel with a hard door. Place all base pieces with hooks on the outside facing down. Module 7, Lesson 4, Task 3
BS-17What are the three types of SSS liners and their typical composition?
The SSS uses three liner types: mid liner, side liner, and end liner. Typical composition: one mid liner, two side liners, and two end liners. All are installed silver side up. Installation order: mid liner first (aligned under center purlin), then side liners (long edge without hook/loop next to mid liner), then end liners (edge with hook/loop straps facing the end arch). Each liner uses purlin cutouts to locate properly on the purlins. Module 7, Lesson 4, Task 3
BS-18What periodic maintenance does the SSS electrical cable assembly require?
Inspect the electrical cable assemblies every 30 days looking for kinks, nicks, or cracks. If found, refer to electricians for repair. The shelter exterior fabric should be inspected for dirt buildup — clean with soap and water only (no solvents, cleaners, degreasers, or abrasives). When the shelter is stored for long periods, inspect at 6-month intervals. Inspect during every assembly and disassembly for missing or broken parts. Module 7, Lesson 4, Task 3
BS-19What is the BEAR kitchen power supply, and which SDCs serve which equipment?
The BEAR kitchen requires a 225 Amp, 208 Volt, 3-phase, 60 Hz power source distributed by two dedicated 150 kVA SDCs (initially fed by one 60 kW and one 30 kW generator). SDC 1 feeds: four walk-in refrigerators, two ACs, and three of four secondary electrical distribution boxes. SDC 2 feeds: grease trap, water heater, water pump, tilting fry pan, AC, and one secondary distribution box. Once the base grid is operational, generators become backup. Module 7, Lesson 3, Task 4
BS-20What is the ESPEK and what are its power requirements?
The ESPEK (Electric Single Pallet Expeditionary Kitchen) provides initial hot meals capability in austere locations. Power: supplied via a 60 kW MEP-806B generator through a 200-amp power cable feeding a 60 kVA PDP. The PDP has five 60-amp Class L box mount receptacles for 208 VAC 3-phase appliances. 110 VAC GFCI duplex convenience outlets are also included. The ESPEK can prepare 550 UGR-H&S rations and 350 UGR-A rations in less than 2 hours. Module 7, Lesson 3, Task 4
// lesson 2 · task 3 · 19.2.6.3
BEAR Grounding Methods
Reference: Module 7 Transcript, Lesson 2, Task 3
BG-01What are the four basic objectives of grounding in BEAR operations?
(1) Minimize damage and service interruptions due to all possible electrical faults including lightning. (2) Reduce overvoltages and insulation damage due to switching, static buildup, and lightning. (3) Minimize injuries to persons near electrical equipment by providing a low-resistance earth path. (4) Minimize noise in communication and control circuits by establishing a solid electrical reference. Key words: "minimize" and "reduce" — eliminating all risk is not possible. Module 7, Lesson 2, Task 3
BG-02What are the four levels of adequate grounding for BEAR operations?
LVST: Low-voltage (≤600V) short-term (usually up to 4 weeks). LVLT: Low-voltage long-term (usually 4 weeks to 2 years). HVST: High-voltage (>600V) short-term. HVLT: High-voltage long-term. These levels were developed for arid, sandy, or rocky areas where 25-ohm grounding is difficult. Traditional grounding works well in coastal/moist areas but corrosion is a significant maintenance problem there. Module 7, Lesson 2, Task 3
BG-03What grounding wire size should be used unless specified otherwise in BEAR grounding?
Unless specified otherwise, equipment should be grounded with #2 or #4 AWG copper wire. For high-voltage systems in very dry, sandy, rocky terrain, a dedicated ground wire is required — this wire serves the same purpose as moist soil in normal environments, ensuring fault currents are driven back to the generator to trip circuit protection. Module 7, Lesson 2, Task 3
BG-04What is the LVST grounding requirement, and what happens if rods cannot be driven?
LVST: Ground generators with a standard ground rod driven next to the generator. If rods cannot be driven, lay them horizontally in a trench 18 inches deep and cover with soil (not rocks). Connect the distribution system neutral conductor from the generator to this ground. As long as this three-phase system has a grounded neutral, further deliberate grounding at other locations is not required. Place generator on an electrical grid platform (concrete or sandbags) tied to a standard ground rod. Module 7, Lesson 2, Task 3
BG-05What is the salt solution treatment for LVLT grounding, and what proportions are used?
For LVLT, treat generator ground rods with salt solutions poured directly on or around the rod to saturate the soil. Treat as water availability permits, repeating as necessary to keep rod contact soil as moist as possible. Proportions: 3 pounds of salt per gallon of water for a good saturated solution. ROWPU brine water also serves well for this purpose. All distribution equipment (transformers, junction boxes, panels) must also be locally grounded with standard ground rods. Module 7, Lesson 2, Task 3
BG-06What is the expedient perforated pipe grounding method for dry sand?
Drive a perforated pipe into dry, loose sand, then fill with a solution of 15 pounds of salt per 5 gallons of water using a funnel. The salt solution percolates into sand and provides a conductive soil for current flow. This ground remains effective until the solution evaporates or drains away — usually several hours to a few days. Disadvantage: tends to corrode the pipe quickly — frequent replacement necessary. Keep the grounding clamp and wire connection clean and corrosion-free. Module 7, Lesson 2, Task 3
BG-07What is the trench ground ring method and where is it best used?
The trench method is most useful in rocky terrain where rods are difficult to drive. Lay bare copper wire in a horizontal trench (usually 18 inches deep) and cover with soil; apply salt solution treatment if available. More wire in the trench provides a better ground. Note: wire becomes unrecoverable after several salt solution treatments due to corrosion. Some field users have successfully used this method without salt solution. Module 7, Lesson 2, Task 3
BG-08What alternate grounding structures/sites can be used when traditional methods are unavailable?
Alternate grounding sites: existing water piping systems, rebar in reinforced concrete (serves as horizontal ground rods), existing metal sewage systems, metal fencing (construct electrical grids), and ground rods driven near operational wastewater dumps, sinks, septic tanks (sewage liquids are normally very conductive). When using sewage proximity: plastic/PVC drain pipe is recommended — prevents injecting current into water systems. Deep wells can tie the entire grounding system to earth potential. Module 7, Lesson 2, Task 3
BG-09What is required for HVST grounding beyond what LVST requires?
In addition to traditional grounding and grounded neutral: a dedicated ground wire must be run from the generator grounding rod to all grounded locations on the base. This wire can be laid in existing trenches, separate trenching, or formed using the concentric ground wires of high-voltage cables. This extra wire provides a common ground plane normally provided by soils and is necessary for adequate personnel safety. Module 7, Lesson 2, Task 3
BG-10What is the HVLT grounding requirement and what water source is used?
HVLT requires the HVST system augmented with grid ground planes for generators and surface-mounted transformers, plus direct contact of the grounding system with a known permanent water source (local water table). Connect the grounding plane and dedicated ground wires to the metal well casing, or lower a copper conductor into the well. If no water well is available, drilling is necessary. Continuous and frequent inspection of grounding connections is critical — cleaning corrosion and protecting connections maintains system reliability and safety. Module 7, Lesson 2, Task 3
BG-11Why does the traditional 25-ohm grounding standard sometimes not apply in bare base operations?
In many bare base locations (especially dry, rocky, or sandy regions), the soil does not permit 25-ohm grounding with traditional ground rods or expedient techniques — the water table is very low and soils are poor conductors. Therefore, bare base grounding uses "adequate by expediency" levels consistent with the construction time phase and distribution system used. The objectives are to "minimize" and "reduce" risk, not eliminate it. Module 7, Lesson 2, Task 3
BG-12What is the ROWPU ground resistance requirement and how is the ground rod installed?
The ROWPU maximum ground resistance must not exceed 25 ohms. The ROWPU comes with a three-piece ground rod stored on the control panel. Install: insert rod-driving bolt into coupler of the first section to protect it while hammering; drive until about 6 inches remain exposed; remove bolt; insert next section into threaded coupler; repeat until all sections are installed. Then secure grounding conductor between ROWPU and ground rod. Check connection security and verify resistance does not exceed 25 ohms. Module 7, Lesson 3, Task 3
BG-13In coastal regions, what makes grounding effective, and what maintenance problem arises?
In coastal regions, high water tables and relatively moist soils with high mineral and salt content make traditional grounding methods provide excellent grounding. However, corrosion of ground connections is a significant maintenance problem because corroded terminals develop their own high resistance. This corrosion can be reduced by frequent inspections, maintenance, and treatment of ground connections. Module 7, Lesson 2, Task 3
BG-14What is the generator platform ground grid requirement for LVST?
Place generators on an electrical grid platform of either concrete or sandbags tied to a standard ground rod driven a few feet away from the platform. The platform must be large enough to permit the generator operator to stand on it while attending the generator. Connect both the generator and the distribution system neutral wire to this ground grid and ground rod. Module 7, Lesson 2, Task 3
BG-15What caution applies when driving ground rods near sewage systems?
Exercise care to ensure that this ground connection does not endanger personnel should a fault occur. The drain pipe must NOT be constructed with metal materials — use plastic or PVC sewage drain pipe if the BEAR equipment ground rod is driven into the moist soil region of a sewage drain. This prevents injection of current into the water systems of a latrine or dining hall. The ground rod is driven into the waste-saturated moist soil region around a septic tank. Module 7, Lesson 2, Task 3
// lesson 3 · task 1 · 19.2.2.1
Remote Area Lighting Systems (RALS)
Reference: TO 35F5-5-22-1
RA-01What does a RALS unit contain, and what power source does it require?
Each RALS unit is an air transportable cabinet weighing approximately 1,500 pounds. It contains: two 750-foot lighting cable assemblies, 13 light masts, 13 light fixtures, 12 mast bases, and 17 lamps. It can be energized from any source providing 120/208 Volt 3-phase power, typically fed from an SDC via a 60-amp cable. The base must be mission ready within 72 hours. Module 7, Lesson 3, Task 1
RA-02How is the RALS cable assembled and how long is each lighting loop?
Cable comes in four 375-foot sections. Connect two 375-foot cables using the 208V 3-phase blue cannon plug connection to make a 750-foot loop cord assembly. Repeat with the remaining two sections for the other half. All four make a complete 1,500-foot lighting loop. Each 750-foot half loop connects to the RALS cabinet. One lighting circuit can only reach 750 feet. Module 7, Lesson 3, Task 1
RA-03How are RALS light poles and junction boxes positioned?
There is a junction box every 125 feet along each lighting loop assembly that feeds the lighting fixture. Place and anchor 12 light mounting pads (one at each of the 12 junction box locations). Place 12 of the 13 telescopic light poles in the mounting pads; secure the 13th pole to the RALS cabinet. Extend poles to full height, secure power cord from fixture to poles, and connect to the junction box. Cables should be installed above ground except in high-traffic areas. Module 7, Lesson 3, Task 1
RA-04What is the RALS operational check sequence including photocell testing?
Set SDC circuit breaker for feeder cable receptacle to ON. Turn on circuit breakers at RALS; set magnetic lighting contactor and photocell override switch to ON — all lights should come on. Repair problems with power off. Apply power and set photocell override to OFF — all lights should go out. Set override to AUTO and cover photocell window with opaque object — lights should come on in about 30-120 seconds. Remove object — system fully operational. Module 7, Lesson 3, Task 1
RA-05What lamp type is commonly used for RALS, and what is the maintenance frequency?
The RALS commonly uses 150-watt HPS (High Pressure Sodium) lamps. All inspections and maintenance actions must be performed quarterly unless otherwise required. The entire system — including the storage cabinet — must be maintained in fully operational status since it can be mobilized at a moment's notice. Correct all discrepancies when found. Module 7, Lesson 3, Task 1
RA-06What are the RALS maintenance inspection points for cables, breakers, and the container?
Lighting Loop Assemblies: ensure connections secure and corrosion-free; inspect cables thoroughly for damaged insulation; excessive corrosion warrants connector replacement. Circuit Breakers and Fuses: check condition and operability; check fuse holders, breaker mounts, and connections for corrosion; repair/replace defective items. RALS Container: check semiannually for structural damage, paint condition, cleanliness, and corrosion; remove corrosion with sandpaper or wire brush and repaint. Module 7, Lesson 3, Task 1
RA-07What are the RALS site selection criteria?
Site selection considerations: any limitations of lighting cables and extent of circuit (one lighting circuit can only reach 750 feet); site should be as nearly level as possible — not critical to be perfectly level; the surface should be firm and well drained to prevent soil from washing out during heavy rains. Connect the feeder cable to the SDC before performing an operational check. Module 7, Lesson 3, Task 1
RA-08What are the RALS uses beyond basic work area lighting?
The RALS can be utilized in other areas such as aircraft parking, munitions storage, and roadway lighting in addition to general work area illumination. It provides a reliable lighting source during hours of darkness and is a critical asset for the 72-hour mission-ready requirement at bare base sites. Refer to TO 35F5-5-22-1 for more guidance. Module 7, Lesson 3, Task 1
RA-09How does the RALS differ from the telescopic floodlight set?
The telescopic floodlight set has advantages over RALS: faster setup time, easier to move around, and most importantly it produces its own power (self-contained 6 kW generator with diesel engine). The RALS requires an external power source (SDC/60-amp cable). The floodlight set is ideal for the first day or so of deployment before site electrical distribution is established. The RALS is better for sustained operations with established power. Module 7, Lesson 3, Task 2
RA-10What is the ROWPU and what are its production rates at different TDS levels?
The ROWPU (Reverse Osmosis Water Purification Unit) is used most frequently on deployments to produce potable water. At less than 1,000 ppm TDS: produces 1,500 gallons per hour. At more than 45,000 ppm TDS: reduced to 1,200 gallons per hour. Operates in temperatures from -25 to +140°F. Unit should be sited upstream from camp, no more than 250 feet from raw water source. Reference: TO 40W4-20-1. Module 7, Lesson 3, Task 3
RA-11What are the ROWPU pump motor specifications?
Reverse Osmosis Pump: 208 VAC 3-Phase, 40 hp, 99.5 amps. Booster Pump: 208/460 VAC, 1 hp, 3.4/1.6 amps (protected by 3-phase 15-amp CB6). Raw Water Pumps (×2): 208 VAC, 3 hp, 8.1 amps; second pump powered from electrical cannon plug on first pump. Distribution Pump: 208/460 VAC, 1 hp, 3.4/1.6 amps (protected by 3-phase 15-amp CB5, fed through receptacle J5). Raw water pumps can also function as backwash pumps for maintenance. Module 7, Lesson 3, Task 3
RA-12What is the PLC in the ROWPU and what makes it different from a general-purpose computer?
A PLC (Programmable Logic Controller) is a digital computer used for automation of electromechanical processes. Unlike general-purpose computers, it is designed for: multiple inputs/outputs, extended temperature ranges, immunity to electrical noise, and resistance to vibration and impact. Programs are stored in battery-backed or non-volatile memory. It is a real-time system — output results must be produced in response to input conditions within a bounded time. The ROWPU's PLC uses input sensors to control the entire water purification process. Module 7, Lesson 3, Task 3
RA-13What is the critical WARNING for ROWPU maintenance?
WARNING: ROWPU piping and equipment can contain extremely high pressure during and after operation. If this pressure is not relieved before working on pipes or equipment, serious injury or death may result. Be sure to open ALL drains and vents before beginning any disassembly. Additionally, the ROWPU must be grounded before use, and the ROWPU's most outstanding feature is that it is designed to be compact, containing all required equipment within its structural confines. Module 7, Lesson 3, Task 3
RA-14What are the telescopic floodlight set generator specs and proper voltage range?
The telescopic floodlight set has a 3-cylinder, 10.5 horsepower, water-cooled diesel engine driving a 6 kW generator capable of supplying 120/240 volts AC. For proper operation, the voltage range should be 233 to 247 volts AC. The main tower reaches a full height of 29 feet. One breaker per 120V outlet and per 1,000-watt lamp. Do not operate starter motor for more than 10 seconds — it may overheat. Allow a 60-second cool-down between cranking intervals. Module 7, Lesson 3, Task 2
RA-15What are the floodlight set maintenance intervals?
Daily: fuel level, engine oil level/condition, coolant level, fuel filter bowl for water, steel winch cables, fuel/oil leaks, tire pressure (min 20 psi, max 60 psi). 250 hours: change engine oil and filter, air filter element, check coolant, check hardware. 500 hours: replace fan belt, clean radiator fins, change fuel filter, inspect fuel tank. 750 hours: lubricate mast. 1,000 hours: inspect cable pulleys, clean and lube, inspect wheel bearings. Module 7, Lesson 3, Task 2
// lesson 3 · tasks 2, 3, 4
Floodlight, ROWPU & Kitchen
Reference: TO 35F5-5-21-1 / TO 40W4-20-1 / TO 35E4-169-1
Note: These questions supplement the detailed RALS section above. Key specs for each system are grouped here for focused review.
FL-01What pre-checks must be done before starting the telescopic floodlight generator?
Before starting: check engine oil level, engine coolant level, fuel level, and that air filter and all intake ductwork are securely clamped. At control panel: ensure all circuit breakers OFF → master control switch ON → press and hold fault bypass push button → press and hold glow plug engage for 10 seconds (continue holding 10 seconds after starting) → press starter switch to crank. Release starter when engine runs; release fault bypass after engine runs 5-10 seconds. Module 7, Lesson 3, Task 2
FL-02How should floodlights be pre-positioned before raising the mast?
Position floodlights from the rear end of the trailer while the tower is in the horizontal position — once raised, positioning requires a ladder. It is easiest to point reflectors outwards about 45 degrees and slightly downwards. If 360-degree coverage is required, point 2 of the lights in the opposite direction. Only raise the main tower once the trailer is stabilized using the four leveling jacks. Release the mast support saddle latch before raising. Module 7, Lesson 3, Task 2
FL-03What are the ROWPU chemical feed pump functions?
Chemical feed pumps are low-amperage diaphragm pumps that move only 2.67 gallons per hour. They are unique in that they simultaneously feed four different chemicals the ROWPU uses. Each feed body dispenses: polymer, sodium hex, citric acid, and chlorine. Suction lines are at the bottom of each feed body; feed lines are on top. They are located to the left of the control box. Module 7, Lesson 3, Task 3
FL-04What power does the ROWPU require?
The 1,500 GPH ROWPU can be powered by a 35 kW generator or commercial power. It has an accessible control panel and is compact enough that all required hoses, bladders, pumps, tools, and test equipment are packed within the structural confines of the unit. It is operable on the ground or mounted on a 5-ton trailer or 5-ton truck. Air, rail, and truck transportable. Module 7, Lesson 3, Task 3
FL-05What is the BEAR kitchen serving capacity and what power step is first required?
The BEAR kitchen facility is designed to serve up to 550 personnel and seat 120. First step in installation: install the SDCs and connect them to a power source. Then install secondary circuits to the four secondary distribution boxes and kitchen equipment directly plugging into SDCs. Final step: install facility lighting. Cables must be buried or protected by a platform in high-traffic areas. Module 7, Lesson 3, Task 4
FL-06What are the BEAR kitchen electrical maintenance checks?
Check the following prior to operation, every week while in operation, and prior to disassembly: (1) All electrical connections of cables, receptacles, circuit breakers, and light assemblies for damage, burned contacts, and insulation breakdown; (2) Attachment security of all electrical items; (3) Light assemblies for burned-out lamps; (4) Ensure equipment is installed correctly and functions properly. Module 7, Lesson 3, Task 4
FL-07What is the junction box location and function on the ROWPU?
The junction box is located immediately to the right of the control panel. It contains the main system disconnect, circuit breakers, control relays, motor starters, and an I/O module. The push button control box (major component on the ROWPU control panel) is where all electrical components are controlled. The pilot light enclosure contains all indicator lights showing operation mode and trouble indicators for potential problems. Module 7, Lesson 3, Task 3
FL-08What are the site prerequisites for any Air Force contingency bare base location?
The Air Force has pre-selected sites throughout the world with only two prerequisites: (1) a suitable landing area; (2) a water source within one mile. The water must be made potable using the ROWPU to sustain base operations. The ROWPU unit must be placed on firm, level ground, upstream from camp, and no more than 250 feet from the raw water source. Module 7, Lesson 3, Task 3
FL-09What is the RALS lamps and fixture quarterly maintenance?
Quarterly (or as required): Lamps and Fixtures: check lamp fixtures and mounting poles for security, condition, and corrosion; check condition of lamps. Circuit Breakers and Fuses: check breakers and fuses for condition and operability; check fuse holders, breaker mounts, and electrical connections for corrosion and broken items; repair or replace defective items. RALS Container: check semiannually for structural damage, paint, cleanliness of storage compartments, and corrosion. Module 7, Lesson 3, Task 1
FL-10What are the BEAR kitchen and ESPEK reference technical orders?
BEAR Kitchen references: TO 35E4-169-1 (Erection, Operation, Storage, Inspection, and Maintenance — Harvest Falcon/Eagle Kitchen Facility) and TO 35E4-169-11 (Operation and Maintenance — Harvest Falcon/Eagle Kitchen Power Distribution System). ESPEK: single pallet expeditionary kitchen providing all initial hot meals capability for AEF deployments; can prepare 550 UGR-H&S rations and 350 UGR-A rations in less than 2 hours. Module 7, Lesson 3, Task 4
// navigation
ROWPU Content
ROWPU questions are in the RALS & Support Systems section (RA-10 through RA-13, FL-03, FL-04, FL-07, FL-08). Use the sidebar to navigate there or continue to MAAS.
// navigation
BEAR Kitchen Content
Kitchen questions are distributed across sections: BS-19 & BS-20 (secondary distribution), FL-05, FL-06, FL-10 (floodlight section). Use the sidebar to navigate there or continue to MAAS.
// lesson 4 · task 1 · 19.1.1.1
Mobile Aircraft Arresting System (MAAS)
Reference: Module 7 Transcript, Lesson 4, Task 1
M-01What is the purpose of the MAAS and how fast can it be certified for use?
The MAAS performs the same function as a fixed aircraft arresting system but focuses on contingency deployment rather than long-term installation. A fully functioning MAAS can be ready for certification in approximately 37 minutes based on three four-man teams with zero installation delays (compared to approximately one day for a permanent BAK-12 install). The MAAS consists of two identical units, one on each side of the runway. Module 7, Lesson 4, Task 1
M-02What are the four main component areas of the MAAS?
The four main component areas: (1) Trailer (energy absorber, body frame, axle support frames, axle cylinders, tow bar assembly, tires, storage box, hydraulic winch, pendant storage reel); (2) Trailer Braking System (hydraulic, emergency, and parking brakes); (3) Installation Tools (HPU, hydraulic breaker, post driver, stake puller, hammer drill); (4) Installation Hardware (anchor plates, taper bolts, flat washers, turnbuckles, stakes, moil points). Module 7, Lesson 4, Task 1
M-03What energy absorber does the MAAS use, and what are the two runout options?
The MAAS uses the BAK-12 as the energy absorber. Standard configuration: 66-inch diameter reel with 990-foot runout. It can be upgraded with a 32-tooth cam sprocket to allow 1,200-foot runout. Each trailer stores a different pendant cable length: one is 90 feet long and the other is 153 feet long, supporting multiple runway widths. Module 7, Lesson 4, Task 1
M-04What is the Hydraulic Power Unit (HPU) and how many are on each MAAS trailer?
The HPU is a portable, engine-driven gear-type hydraulic pump. There are two HPUs per trailer, one on each side. They power the various hydraulic tools and systems on the MAAS. Two 50-foot hoses connect each tool to the HPU. The HPU powers: hydraulic breaker, post driver, stake puller, hammer drill (auxiliary power tools), and the hydraulic winch for loading into aircraft. Module 7, Lesson 4, Task 1
M-05Describe the MAAS battery position and what it maintains.
Battery position is when the shuttle valve is in the ON position, applying 175 ±10 PSI static pressure from accumulator to the brakes. This continual pressure maintains pretension in the pendant cable — preventing sag and allowing the aircraft tail hook to successfully engage the pendant. This is the ready-to-arrest position. Module 7, Lesson 4, Task 1
M-06How does the MAAS arrest an aircraft — describe the hydraulic sequence.
Aircraft tail hook engages pendant. Forward motion pulls pendant down runway; purchase tapes unwind from storage reel, driving the hydraulic pump and cam via chains/sprockets. The cam rotates clockwise toward 270°, operating the cam control valve — valve closes to increase restriction to fluid flow. When hydraulic pressure exceeds the static accumulator pressure, the shuttle valve moves to OFF. Increasing pressure applies to friction brakes, slowing the tape reel. When aircraft stops, all pressure is relieved through the cam control valve back to reservoir. Module 7, Lesson 4, Task 1
M-07What is the retraction time for MAAS and how does the retraction system work?
Retraction time is 3 minutes for 990-foot runout and 3.5 minutes for 1,200-foot runout. The rewind engine connects to the storage reel shaft via PTO, fluid coupling, gear reducer, and chains. The fluid coupling permits torque to be applied while the output shaft is "stalled" — engine torque is transmitted to the rewind sprocket for pre-tensioning. Reel rotation is stopped by tape tension when fully retracted. Pre-tension is maintained by static accumulator pressure when shuttle valve resets to ON. Module 7, Lesson 4, Task 1
M-08What are the four MAAS installation configurations and their key differences?
Concrete: 2 anchor plates; remove one tire on pilot's right; only installation requiring tire removal. Soil: 19 stakes for unidirectional (10 body + 9 for 3 stake lines); 31 stakes for bidirectional (10 body + 21 for 7 stake lines); maintain 15° stake angle. Asphalt over concrete (>1 inch): 10 moil points in stake pockets; no tire removal. Asphalt over soil: chip asphalt where stakes install; same as soil otherwise. Bi-directional concrete: 3 anchor plates, remove 2 tires per MAAS. Module 7, Lesson 4, Task 1
M-09What is the trailer positioning formula relative to pendant cable length?
Trailers should be positioned for cable length + 15 feet unless setbacks will be used. For bi-directional installation: position trailers so the distance between the two trailers is cable length + 15 feet. Setback kits with additional equipment can be used to allow for wide-bodied aircraft. Stake lines off the triple turnbuckle must maintain an approximate 15° separation between stake lines. Module 7, Lesson 4, Task 1
M-10What are the MAAS preventive maintenance schedules for key components?
Hook cable: Replace every 36 months when installed or 60 months when stored. Tape: crop ends every 6 months; replace per governing guidance when installed or after 60 months stored. Hydraulic system: synchronize/proof test after initial install, every 3 months after install, every 12 months while stored. Arresting system functional checkout: every month installed, every 6 months stored. Coolant pumps: operate every month installed, every 12 months stored. Inspect weekly and after each arrestment for loose/worn parts and anchor assembly security. Module 7, Lesson 4, Task 1
M-11What are MAAS tires filled with and why is caution required when removing them?
MAAS tires are filled with urethane foam for puncture resistance and weigh approximately 410 pounds. Extreme caution should be taken when removing or installing wheels during installation and removal due to the weight. The tow bar assembly has a pintle hook for single or tandem towing — reducing the requirement for multiple tow vehicles and the risk of FOD onto the runway. Module 7, Lesson 4, Task 1
M-12Why must anchor stakes not enter the tape path during soil installation?
Anchor stakes must not enter the tape path because it will damage the purchase tape during arrestment, potentially causing damage to aircraft and/or loss of life. Also regarding stake orientation: properly orient stakes for the stake puller on site so the stake puller won't severely damage them upon removal. The stake puller intentionally pinches the stake between two teeth — any body part caught between stake and teeth will cause severe injury. Module 7, Lesson 4, Task 1
M-13What are the three MAAS braking systems and their functions?
Hydraulic Braking System: braking assistance during towing; master cylinder actuated when trailer pushes against slowing tow vehicle. Emergency Brake System: breakaway cable attached to a breakaway lever — if unit separates from vehicle during towing, lever unlocks and applies hydraulic pressure to slow MAAS. Parking Brake System: single lever with over-center locking feature, mounted on rear axle, applies brakes to rear wheels only. Module 7, Lesson 4, Task 1
M-14What is the air cleaner service indicator for the MAAS Wisconsin engine?
Clean the air cleaner every 6 months for a Wisconsin engine. Service the air cleaner when the red signal is fully visible when the engine is off. Oil filter replacement: every other oil change. Inspect the system for loose or worn parts and anchor assemblies for security weekly and after each arrestment. Severe damage to equipment, aircraft, and loss of life could occur if anchor assemblies are not secure. Module 7, Lesson 4, Task 1
M-15What is the hammer drill used for in MAAS installation and what quality control exists?
The hammer drill is used exclusively for concrete installation — drilling holes to install taper bolts. To ensure holes are drilled as close to 90° to the surface of the concrete pad as possible, two observers monitor the drill operator for tilting and provide feedback for corrections. Taper bolts secure anchor plates to the concrete pad; flat washers distribute the force of tightening by increasing surface area. Module 7, Lesson 4, Task 1
M-16What is the body frame's role in the MAAS?
The Body Frame supports all arresting gear components, supports the tape guide system, and has an internal set of 5 sheaves which allow for free travel of tape off the reel. It transmits loads to the ground just like fixed arresting system concrete pads. The axle support frames provide structural support for front and rear axle assemblies and serve as a mechanical link to the hydraulic cylinders that raise and lower the trailer. Module 7, Lesson 4, Task 1
M-17What additional uses does the MAAS have beyond contingency airfields?
The MAAS can be used for air shows like the Thunderbirds or Blue Angels since some air shows are at civilian airports without arresting system support. The MAAS is also useful when the installation cost of permanently installed aircraft arresting equipment exceeds the return on investment. The MAAS's transportability via air and land creates a variety of transportation options to the installation site. Module 7, Lesson 4, Task 1
M-18What are the MAAS asphalt over concrete bidirectional installation unique requirements?
For asphalt over concrete bidirectional installation: no body stakes are installed, therefore only 21 stakes are necessary (vs 31 for soil bidirectional). To install the stakes, remove the asphalt where the stakes will be installed. There is no difference between bidirectional and unidirectional when it comes to asphalt over concrete methods — both use 10 moil points. If asphalt is less than 1 inch thick, use the concrete installation method instead. Module 7, Lesson 4, Task 1
M-19What safety warning applies to MAAS towing speed?
The MAAS trailers are not designed for use on public roads and highways — they are not equipped with taillights, brakes, or clearance lights (same restriction as EALS trailers). The MAAS can be towed in convoy. The pintle hook allows tandem towing to reduce the requirement for multiple tow vehicles and the risk of FOD being brought onto the runway. The similarity between MAAS and permanently installed systems facilitates easy transitioning between maintaining either. Module 7, Lesson 4, Task 1
M-20What does the pendant storage reel store and why are two different lengths provided?
The pendant storage reel stores the pendant cable and allows for easy deployment during installation. One trailer stores a 90-foot pendant and the other stores a 153-foot pendant. This difference in lengths allows the MAAS to support multiple runway widths — narrow runways use the shorter pendant; wider runways or setback configurations use the longer pendant. Together, the two trailers can accommodate any standard runway width. Module 7, Lesson 4, Task 1
// lesson 4 · tasks 1-2 · 19.2.1.1.1
BEAR Shelter Lighting
Reference: TO 35E5-6-11 (SSS) / Module 7 Transcript
SH-01What are the three major components of the BEAR tent interior lighting/power distribution system?
The three major components: (1) Distribution box; (2) Two convenience outlet assemblies; (3) Incandescent light streamer assembly. Each tent receives one light streamer (six lights spaced along it) and two convenience outlet assemblies (one per side). The distribution box is fed from a PDP by a 50-foot, 20-amp cable with twist-lock connection. Module 7, Lesson 4, Task 1
SH-02What protection devices are in the BEAR tent distribution box?
The distribution panel has a single-pole toggle switch protected by a 20-amp circuit breaker to control the lights. Two GFCI 20-amp circuit breakers protect an outlet streamer for each side within the tent. Both the light streamer and outlet streamers connect to the distribution panel with twist-lock connections. The 3 cables with female connectors are for string lights and receptacles. Module 7, Lesson 4, Task 1
SH-03What are the light spacing specs for SSS tent electrical installation?
Install lights starting from the distribution box. String first three lights to purlins on the left side of shelter, approximately 10 feet apart. Continue running cable over and alongside the fifth arch to purlins on the right side. Attach the next three lights about 10 feet apart. Connect receptacle strings: 39-foot string (4 receptacles) runs left side; 50-foot string (4 receptacles) runs right side. Attach a receptacle at each arch frame, approximately 2 feet high. Module 7, Lesson 4, Task 3
SH-04What frayed cable action must be taken during BEAR shelter teardown?
Use proper repair techniques or replace any cable or streamer that may have become frayed. Frayed cables and conductors may cause electric shock or start a fire. During teardown: de-energize first, disassemble in reverse order, clean items during removal, allow wet components to dry before packing (prevent mold), put all components into proper storage containers to ensure rapid reinstallation. Module 7, Lesson 4, Task 1
SH-05What are the SSS safety items that must be followed during assembly?
Wear safety glasses when driving stakes and anchors with a hammer. Wear gloves to handle structural components or pull-on ropes. Frame members are under spring tension and could spring back — beware of frame member rebound. Never use a combustible heating device inside without proper ventilation. Use adequate personnel for heavy components. Never allow snow/ice buildup on top. Never drag fabric over ground or sharp objects. Never pound on pins or slip-fit connections. Module 7, Lesson 4, Task 3
SH-06What site area is needed for SSS setup and what are the pre-setup requirements?
Select an area at least 30 by 40 feet. Ensure the area is free of debris, has adequate drainage, and is as smooth and level as possible. Unlatch top latches and remove the container top. Unpack components keeping like items together. When removing items, inspect for damage or missing parts. After all items are removed, reinstall the container top for storage — store it this way until needed again. The SSS has been designated as the replacement for the TEMPER tent through attrition. Module 7, Lesson 4, Task 3
SH-07How is the ECU (Environmental Control Unit) positioned and connected to the SSS?
Using a forklift, place the ECU on the most level area in front of the shelter duct openings, approximately 12 inches away from the shelter end wall. The side labeled EXHAUST END must face toward the shelter duct openings. The supply duct (no wire ring supports) attaches to the supply air vent and goes through the right-hand fabric boot. The return air duct uses the left-hand fabric boot. ECUs should only be inspected and repaired by HVAC/R personnel. Module 7, Lesson 4, Task 3
SH-08What is the cover installation sequence for the SSS main cover?
Lay cover next to shelter — black side faces inside. Secure one end of cover base rope to silver tie-off cleat; stretch and secure other end. Attach four pullover ropes to the four black loops at the base. With one person on each rope: end persons pull at 45 degrees toward outside; middle two pull straight back — this ensures even fabric pull across arches. Secure base rope on the other side. Work cover over ends with ladder/persons; ensure 4-5 inch overlap equal on both ends. Tension contour rope; attach base rope to hooks with hook tools. Module 7, Lesson 4, Task 3
SH-09What are the two types of SSS end panels, and what is unique about the hard door installation?
Two end panel types: zippered and hard door. Hard door unique steps: make sure door is installed with white side facing inside; place doorframe so the stub slides into the spike hole in the center end base frame; from inside, slide header stubs into top of doorframe and secure with pins; install doorknob and adjust strike mechanism. After either type: install a plastic vent cap at the top center of each end panel (Velcro secured) for ventilation. Module 7, Lesson 4, Task 3
SH-10What is the SSS disassembly first step, and what special tools/precautions are needed?
First step: make sure all power is disconnected from the electrical system at the source. During disassembly: pullover ropes are NOT needed to remove the cover. If pins are tight, do not force — gently tap or wiggle them loose. Do not drop or throw objects from high elevations. To raise spike heads: use the spike puller with dunnage directly under spikes to prevent damage. Be sure cover and end wall panels are dry before packing. Disassemble in reverse order of erection. Module 7, Lesson 4, Task 3
Roadmap